A couple of months have now passed and our new building is really starting to take shape. All interior and exterior walls are now completed and have been plastered, painted and ready for the lighting to be installed. We are only a few weeks away from our moving date so keep your eyes peeled for the big reveal.


David Village Lighting


Interior walls of the staff area plastered and ready for painting.


David Village Lighting


The office painted and ready for the carpets to be laid and lighting to be installed.


David Village Lighting


Stairs and banisters all in place on the warehouse mezzanine.


David Village Lighting


The new showroom, 3 times the size of our current, plastered and ready for the under floor heating to be installed.


David Village Lighting


The beginning of the new lobby area being built.


David Village Lighting


 Under floor heating being fitted in the showroom.


David Village Lighting


The new concrete floor being poured and left to cure in the showroom.


David Village Lighting


The exterior walls formed and ready for signage.